New Delhi: (PTI) Prime Minister Narendra Modi on Monday virtually laid foundation stones of three hydro-electric power projects of 658 MW capacity, entailing an investment of Rs 5,564 crore, which are implemented by SJVN in Himachal Pradesh.
Modi also launched the ground-breaking ceremony of the 382 MW Sunni Dam project located in Shimla and Mandi districts.
Himachal Pradesh Governor Rajendra Vishwanath Arlekar, Chief Minister Jai Ram Thakur, Union Minister of I&B and Youth Affairs & Sports Anurag Thakur were also present on the occasion.
These projects are being implemented by SJVN on a build-own-operate-maintain (BOOM) basis.
The Luhri-1 project and Sunni Dam project are on the Satluj river and Dhaulasidh project is on the Beas river.
Nand Lal Sharma, Chairman & Managing Director, SJVN stated that in November 2020, the Cabinet Committee on Economic Affairs approved 210 MW Luhri-1 Hydro Electric Project at a cost of Rs 1,810 crore.
The project is scheduled to be commissioned by January 2026. On completion, it would generate 758.20 million units of electricity annually. The project has also been accorded budgetary support of Rs 66 crore. He added that Luhri -1 Project shall generate 20 lakh man-days job opportunities while Himachal Pradesh would immensely benefit with free power worth around Rs 1,140 crore during the project life cycle of 40 years.
Sharma stated that the government approved the project cost of Rs 687.97 crore for 66 MW Dhaulasidh hydroelectric project and has also accorded budgetary support of Rs 21.6 crore.
The project is targeted for completion in November 2025. On completion, this project will add 304 million units of energy annually. The project would result in the creation of 8 lakh man-days employment opportunities while Himachal Pradesh would benefit with free power worth Rs 461 crore from the project.
Sharma further said that the project cost for 382 MW Sunni Dam project has been estimated at Rs 2,614.51 crore which on completion is expected to generate 1,382 million units of electricity annually.
Sharma stated that the government approved the project cost of Rs 687.97 crore for 66 MW Dhaulasidh hydroelectric project and has also accorded budgetary support of Rs 21.6 crore.
The project is targeted for completion in November 2025. On completion, this project will add 304 million units of energy annually. The project would result in creation of 8 lakh man-days employment opportunities while Himachal Pradesh would benefit with free power worth Rs 461 crore from the project.
Sharma further said that the project cost for the 382 MW Sunni Dam project has been estimated at Rs 2,614.51 crore which on completion is expected to generate 1,382 million units of electricity annually.
This project would help in the reduction of 11 lakh tons of carbon dioxide from the environment annually and Himachal Pradesh would benefit with around Rs 2,587 crore worth of free power.
Sharma stated that the construction of these three Projects involves a total outlay of Rs 5,113 crore and would add over 2,444 million units of electricity generation to the Nation’s capacity annually.
Besides providing with 100 units of free electricity per month for ten years to the Project Affected Families, these Projects on completion would usher in an era of overall Socio-Economic development and prosperity in the region for generations to come.